DEMOThis site is a demo built by Briefikir. Contact us for your own construction company website and admin panelA Briefikir demo — contact us for your own siteSkip to content
Ongoing projects

Transparency Centre

Follow each site’s progress, work packages and dated diary here. Data is updated weekly by the project teams.

Active sites
5
Average progress
%60
Diary entries
21

Göztepe Urban Renewal — 4 Blocks

İstanbul / Kadıköy · 412 independent units

Project page
Overall progress%64
3 pts ahead of programme
Start
September 2024
Expected completion
June 2027
Remaining
8 months
Last update
3 October 2026 (2 days ago)

Work packages

  • Excavation and foundations%100
  • Structural frame%92
  • Façade and glazing%58
  • Mechanical services%47
  • Electrical services%44
  • Finishes and interiors%21
  • Landscaping and external works%0

Planned / actual

02550751002024/092027/06Today
Planned Actual

Site diary

  1. Block C 11th-floor slab poured

    The last typical slab on Block C was poured with 186 m³ of C35 concrete and covered for curing. Roof wall formwork starts on Monday.

    146 on site Sunny, 21°C
  2. Block B façade scaffolding complete

    Scaffolding now wraps all four sides of Block B and insulation boards are going up. A sample façade panel was presented to owners at the monthly meeting.

    138 on site Partly cloudy, 19°C
  3. Block D wall reinforcement inspected

    Wall rebar and cover on the 8th floor of Block D were inspected with the building control firm; the report was signed and pouring approved.

    131 on site Sunny, 24°C
  4. Mechanical risers opened on Block A

    Installation of potable and waste water risers began on Block A. The first three floors are ready for pressure testing.

    124 on site Clear, 26°C
  5. Hot-weather concreting plan in effect

    Pours moved to 05:00 and the batching plant is using chilled water. Slabs are water-cured for seven days after each pour.

    152 on site Hot, 31°C
  6. Owners’ site visit

    42 owners toured Blocks A and B after a safety briefing; the sample flat’s rough dimensions were shown on site.

    117 on site Sunny, 29°C

Percentages show physical progress weighted by the programme. This is a demo: projects and figures are sample data, updated from the panel.