Transparency Centre
Follow each site’s progress, work packages and dated diary here. Data is updated weekly by the project teams.
- Active sites
- 5
- Average progress
- %60
- Diary entries
- 21
Göztepe Urban Renewal — 4 Blocks
İstanbul / Kadıköy · 412 independent units
- Start
- September 2024
- Expected completion
- June 2027
- Remaining
- 8 months
- Last update
- 3 October 2026 (2 days ago)
Work packages
- Excavation and foundations%100
- Structural frame%92
- Façade and glazing%58
- Mechanical services%47
- Electrical services%44
- Finishes and interiors%21
- Landscaping and external works%0
Planned / actual
Site diary
Block C 11th-floor slab poured
The last typical slab on Block C was poured with 186 m³ of C35 concrete and covered for curing. Roof wall formwork starts on Monday.
146 on site Sunny, 21°CBlock B façade scaffolding complete
Scaffolding now wraps all four sides of Block B and insulation boards are going up. A sample façade panel was presented to owners at the monthly meeting.
138 on site Partly cloudy, 19°CBlock D wall reinforcement inspected
Wall rebar and cover on the 8th floor of Block D were inspected with the building control firm; the report was signed and pouring approved.
131 on site Sunny, 24°CMechanical risers opened on Block A
Installation of potable and waste water risers began on Block A. The first three floors are ready for pressure testing.
124 on site Clear, 26°CHot-weather concreting plan in effect
Pours moved to 05:00 and the batching plant is using chilled water. Slabs are water-cured for seven days after each pour.
152 on site Hot, 31°COwners’ site visit
42 owners toured Blocks A and B after a safety briefing; the sample flat’s rough dimensions were shown on site.
117 on site Sunny, 29°C
Percentages show physical progress weighted by the programme. This is a demo: projects and figures are sample data, updated from the panel.