
Göztepe Urban Renewal — 4 Blocks
Nine high-risk 1970s buildings replaced by 412 units over four blocks, with covered parking and shared amenities.
A joint renewal project carried out with the owners of nine adjoining buildings in Göztepe. The flat-for-land agreement is tracked through monthly owner briefings and the site diary on this page from demolition to handover.
The structure was designed to current seismic code on the basis of a geotechnical survey and performance analysis. The four blocks share a single basement car park; the ground level is entirely pedestrian and green.
On site this week
- Start
- September 2024
- Expected completion
- June 2027
- Remaining
- 8 months
- Last update
- 3 October 2026 (2 days ago)
Work packages
- Excavation and foundations%100
- Structural frame%92
- Façade and glazing%58
- Mechanical services%47
- Electrical services%44
- Finishes and interiors%21
- Landscaping and external works%0
Planned / actual
Site diary
Block C 11th-floor slab poured
The last typical slab on Block C was poured with 186 m³ of C35 concrete and covered for curing. Roof wall formwork starts on Monday.
146 on site Sunny, 21°CBlock B façade scaffolding complete
Scaffolding now wraps all four sides of Block B and insulation boards are going up. A sample façade panel was presented to owners at the monthly meeting.
138 on site Partly cloudy, 19°CBlock D wall reinforcement inspected
Wall rebar and cover on the 8th floor of Block D were inspected with the building control firm; the report was signed and pouring approved.
131 on site Sunny, 24°CMechanical risers opened on Block A
Installation of potable and waste water risers began on Block A. The first three floors are ready for pressure testing.
124 on site Clear, 26°CHot-weather concreting plan in effect
Pours moved to 05:00 and the batching plant is using chilled water. Slabs are water-cured for seven days after each pour.
152 on site Hot, 31°COwners’ site visit
42 owners toured Blocks A and B after a safety briefing; the sample flat’s rough dimensions were shown on site.
117 on site Sunny, 29°C
İstanbul / Kadıköy
Map location is indicative.
You may also like
Planning a similar project?
Send us your details in four steps with the quote wizard.


