Ongoing · Sakarya
Adapazarı River Bridge and Link Roads
A 420 m post-tensioned bridge over the Sakarya River with junction links on both banks.
The main span is 110 m. The deck is cast in 5 m segments, advancing symmetrically from two main piers by balanced cantilever.
River-bed works are scheduled around flood seasons; temporary working platforms are removed before every spring.
Related services
Transparency board
All sites On site this week
Overall progress%82
3 pts behind programme
- Start
- November 2024
- Expected completion
- December 2026
- Remaining
- 2 months
- Last update
- 4 October 2026 (1 days ago)
Work packages
- Piles and pier foundations%100
- Piers and pier heads%100
- Deck (balanced cantilever)%88
- Post-tensioning and grouting%79
- Link roads and junctions%72
- Barriers, lighting, waterproofing%24
Planned / actual
Site diary
Two segments to closure
Segment 21 was cast on the west cantilever. Alignment surveys for the closure segment will be taken at night.
98 on site Rainy, 15°CTendon grouting
16 ducts on the east cantilever were grouted and samples sent to the lab.
94 on site Cloudy, 18°CAsphalt on the north junction
The binder course was laid on the north junction arms and temporary traffic management was updated.
88 on site Sunny, 24°C
Location
Sakarya / Adapazarı
Map location is indicative.
Loading map…
Similar projects
You may also like
Planning a similar project?
Send us your details in four steps with the quote wizard.