Ongoing · İzmir

Ilıca Thermal Hotel

A 260-room thermal hotel on seismic isolators, 300 m from the sea in Çeşme.

The building rests on 148 lead-rubber isolators. The isolation level has 1.8 m clear height for inspection and maintenance.

The thermal water loop was designed with heat-recovery exchangers to cover a large share of hot-water demand. Interior fit-out follows the operator’s brand standards.

Transparency board

On site this week

All sites
Overall progress%71
3 pts ahead of programme
Start
January 2025
Expected completion
April 2027
Remaining
6 months
Last update
1 October 2026 (4 days ago)

Work packages

  • Excavation and foundations%100
  • Structural frame%100
  • Façade and glazing%76
  • Mechanical services%62
  • Electrical services%58
  • Finishes and interiors%34
  • Landscaping and external works%12

Planned / actual

02550751002025/012027/04Today
Planned Actual

Site diary

  1. Mock-up room approved

    The mock-up room was walked with the operator and interior designer; a 14-item snag list will be closed within ten days.

    167 on site Sunny, 23°C
  2. Spa pool water-tightness test

    The thermal pool shell passed its 72-hour water test; tiling preparation has started.

    158 on site Windy, 21°C
  3. Conference hall steel roof

    Roof trusses spanning 28 m over the conference hall were lifted over two nights without road closures.

    149 on site Clear, 27°C
  4. East wing window installation

    Aluminium windows for 96 rooms in the east wing were installed and water-tested.

    143 on site Hot, 33°C