Ongoing · Kayseri
Kocasinan Education Campus
A campus of faculty buildings, a central library and student housing on an 18-hectare site in Kayseri.
The programme was phased around winter: structures will be topped out by November so that interior works continue under cover through the cold months.
Precast façade panels are produced at a plant 40 km away, each tracked with a QR code.
Related services
Transparency board
All sites On site this week
Overall progress%37
3 pts behind programme
- Start
- June 2025
- Expected completion
- September 2027
- Remaining
- 11 months
- Last update
- 30 September 2026 (5 days ago)
Work packages
- Excavation and foundations%100
- Structural frame%64
- Façade and glazing%12
- Mechanical services%18
- Electrical services%15
- Finishes and interiors%0
- Landscaping and external works%0
Planned / actual
Site diary
Library reaches roof level
The library’s top slab was poured; steel roof fabrication is 60% complete in the shop.
121 on site Cool, 12°CDormitory level 3
The dormitory block reached level 3 with a one-floor-per-day tunnel-form cycle.
116 on site Sunny, 17°CFaculty B foundation pour
1,240 m³ were poured continuously over 19 hours into Faculty B’s raft.
109 on site Clear, 21°C
Location
Kayseri / Kocasinan
Map location is indicative.
Loading map…
Similar projects
You may also like
Planning a similar project?
Send us your details in four steps with the quote wizard.